How to File a Mechanics Lien in Washington: The 90-Day Deadline

How to file a mechanics lien in Washington, step by step: the 90-day recording deadline, required contents, service on the owner, and the 8-month clock.

Published Last Updated Read Time 7 min readBy ROI Law Firm
ROI Law Firm guide on how to file a mechanics lien in Washington: a framed house under construction on a sunny Pierce County lot with Mount Rainier behind it.

A Washington construction lien has one deadline that cannot be fixed afterward: the claim must be recorded not later than 90 days after the last day the claimant furnished labor, professional services, materials, or equipment (RCW 60.04.091). Record on day 91 and there is no lien. Learning how to file a mechanics lien in Washington is mostly learning to count that period and get the paperwork right.

This guide is for contractors, subcontractors, suppliers, and property owners in Tacoma and Pierce County, Eastside King County (Bellevue, Issaquah, Sammamish), Snohomish County, and Kitsap County.

The short version for contractors and suppliers

  • Record the claim of lien in the county where the property sits within 90 days after you last furnished labor, services, materials, or equipment (RCW 60.04.091).

  • The claim must carry your contact details, first and last furnishing dates, the person who owes you, the owner, a property description, and the principal amount, signed and acknowledged (RCW 60.04.091).

  • Within 14 days of recording, serve a copy on the owner by certified or registered mail or personal service, or forfeit fees and costs against the owner (RCW 60.04.091).

  • Suppliers and lower-tier subs must have sent a preclaim notice first (RCW 60.04.031). The lien lasts eight calendar months unless a foreclosure action is filed (RCW 60.04.141).

How to file a mechanics lien in Washington, step by step

  • What the statute actually says

  • Step one: confirm the preclaim notice

  • Step two: count the 90 days

  • Step three: draft and record the claim

  • Step four: serve the owner within 14 days

  • A worked example: a Puyallup framing contractor

  • Step five: the eight-month clock

  • Where liens are recorded

What the statute actually says

Who has a lien, and for how long

Anyone furnishing labor, professional services, materials, or equipment for the improvement of real property at the owner's request has a lien under RCW 60.04.021. RCW 60.04.091 requires the claim to be filed for recording not later than 90 days after the claimant ceased furnishing professional services, materials, or equipment, or labor, counted from the last day of furnishing, not the invoice date.

Required contents

The notice of claim of lien must state the claimant's name, phone, and address; the first and last furnishing dates; the person indebted to the claimant; the owner or reputed owner, or that the owner is not known; a street address, legal description, or other description identifying the property; and the principal amount claimed. It must be signed and acknowledged under chapter 64.08 RCW.

Service on the owner

A copy must be given to the owner within 14 days of recording, by certified or registered mail or by personal service, or the claimant forfeits attorney fees and costs against the owner (RCW 60.04.091).

Step one: confirm the preclaim notice

First check whether you needed to send a notice of right to claim a lien under RCW 60.04.031. It is not required of persons, including subcontractors, who contract directly with the owner, of laborers claiming only for their own labor, or of subcontractors who contract directly with the prime contractor, with a carve-out for some owner-occupied remodels. Suppliers, equipment lessors, design professionals, and lower-tier subs must have given it.

The notice is given by certified or registered mail, or by delivering or serving the notice personally upon the owner and keeping a receipt. It protects only work furnished after the date 60 days before it was given, or 10 days on new single-family construction. A missing notice shrinks what the lien can reach.

Related: RCW 18.27.114 requires a registered contractor to give the customer a written disclosure statement before the repair, alteration, or construction of a commercial building when the bid or contract price is $1,000 or more but under $60,000.

Step two: count the 90 days

Day zero is your last day of furnishing. Pin it to a delivery ticket, timesheet, or daily log; the owner will argue for an earlier date.

Punch-list and warranty visits are the trap. Returning to fix a defect generally does not restart the period.

No weekend extension. RCW 60.04.091 says nothing about Saturdays, Sundays, or legal holidays moving the 90th day, so do not plan on one.

Step three: draft and record the claim

Draft the claim with every element RCW 60.04.091 lists. The two that go wrong most are the property description and the amounts claimed. Use the full legal description from the parcel record, not a street address alone, and claim only the principal owed for the services, materials, or equipment furnished. An overstated claim invites a motion to release the lien and a fee award against you, which is why a Mechanics lien attorney checks the figure against the ledger first.

File the claim with the county recorder where the property sits: the Pierce County Auditor for Tacoma and Puyallup. The recording date is what the 90 days are measured against.

Step four: serve the owner within 14 days

Recording is not the end of filing a claim of lien. Within 14 days after recording, give a copy to the owner by certified or registered mail or by personal service, and keep the receipt or proof of service. Miss this and the lien still exists, but the fee shifting that makes foreclosure worth pursuing is gone.

A worked example: a Puyallup framing contractor

A framing subcontractor finishes a $48,000 contract on a new house in Puyallup on June 2, per the crew's timesheet, and has been paid $30,000. The prime contractor stops returning calls in July.

The framer contracted directly with the prime, so no preclaim notice was required. Day 90 after June 2 is August 31. The framer records a claim with the Pierce County Auditor on August 28: first and last dates April 14 and June 2, the prime as the person indebted, the owner, the legal description, and $18,000 as the principal amount claimed. On September 3 a copy goes to the owner by certified mail, inside the 14-day window.

The lien binds the property until April 28, eight calendar months after recording. If the $18,000 is unpaid by then, a lien foreclosure action must already be on file in Pierce County Superior Court, or the lien expires.

Myth: "I have 90 days from my last invoice"

Myth: "The 90 days run from the date of my final invoice or the owner's last payment." No. RCW 60.04.091 counts from the day the claimant ceased to furnish labor, professional services, materials, or equipment. A late invoice does not move the deadline and a partial payment does not restart it. Contractors who count from the bill routinely file a lien late.

Step five: the eight-month clock

A recorded lien is leverage, not payment. Under RCW 60.04.141 it binds the property for eight calendar months after recording, and only a foreclosure action filed in superior court inside that window keeps it alive, with the owner served within 90 days of filing. The case must reach judgment within two years or the court may dismiss it, and dismissal cancels the lien. Most liens settle first; a lien on title stops a sale or refinance.

For property owners: a lien recorded late, missing an element, or claiming more than is owed can be attacked by motion under RCW 60.04.081, with fees to the winner.

Where liens are recorded

Pierce County. Tacoma, Puyallup, Gig Harbor, and Lakewood, recorded with the Pierce County Auditor.

Eastside King County. Bellevue, Issaquah, and Sammamish.

Snohomish County. Everett, Lynnwood, and Marysville.

Kitsap County. Bremerton, Silverdale, and Port Orchard.

The construction lien Washington contractors record is governed by the same 90-day, 14-day, and eight-month rules in every county. Only the recording office and courthouse change.

Frequently Asked Questions

How long do you have to file a mechanics lien in Washington?

Ninety days after the last day you furnished labor, services, materials, or equipment (RCW 60.04.091). The mechanics lien Washington deadline runs from furnishing, not invoicing.

What must a Washington claim of lien contain?

Your name, phone, and address; first and last furnishing dates; the person who owes you; the owner; a legal description; and the principal amount claimed, signed and acknowledged.

Do I have to send the owner a copy of the lien?

Yes, within 14 days of recording, by certified or registered mail or by personal service. Skipping it forfeits your attorney fees and costs against the owner.

How long is a construction lien valid in Washington?

Eight calendar months after recording, unless a foreclosure action is filed in superior court within that period (RCW 60.04.141).

Before the 90th day

Filing a Washington construction lien is a sequence: confirm the preclaim notice, count 90 days from the last day of furnishing, record a claim with every element in RCW 60.04.091, serve the owner within 14 days, and calendar the eight-month deadline under RCW 60.04.141. Each step is simple, and each is where liens die.

If you have unpaid work in Tacoma, Pierce County, or the Eastside, Snohomish, or Kitsap markets, send the contract, the last timesheet or delivery ticket, and the parcel number before the clock gets close. A Mechanics lien attorney at ROI Law Firm will fix the dates in writing, draft a claim that survives a motion, and calendar the foreclosure.

Free case reviewTell us what is happening at your property

Submitting this form does not create an attorney-client relationship.

Home

Home

Have a question about your property?

Have a question about your property?

Whether it's a notice, a lease, an eviction, or a deal under review, tell us what's going on and a Washington landlord-tenant attorney at ROI Law Firm will get back to you.

Book a consultation →